CSE 110: Deliverable 1

Planning and Scheduling

(Due date: Due the short time frame forthe project, this deliverable will be due the third class meeting, Thursday, 10/7/99
Note new deadline: 10/12/99, Tuesday, in class)

The planning document should contain the following sections.

1. Scope
    Goals, major functions, system components

2. Size and effort estimates
    Historical sources
    Size estimation - LOC
    Effort estimation  - man/months

3. Risk management
    Project risks
    Risk Table and RMMM plan for each risk
4. Schedule
    Task breakdown
    Task network
    Gannt chart

5. Organization
    Team shtructure
    Team member responsibilities

6. Tracking and control
    Methods to be used - e.g. tracking table
    QA methods to be used (leave this blank for now since
        we have not yet covered them in class)