Students will be required to carry out a class project, which will have four deliverables that will be due at various times during the course. The project must be done in groups of from 3 to 5 students.The deliverables are: project plan, requirements, design, program and testing.
Each project group must find a customer for their project. Examples include employers, customer organizations, membership groups (e.g. sports clubs, church groups, social groups). In coming up with a project you must take into account that you only have 10 weeks for the entire project.
(Due date: Due the short time frame forthe project, this deliverable will be due the third class meeting, Thursday, 10/7/99 Deliverable one: planning and scheduling
Note: New deadline: 10/12/99, Tuesday, in class)The planning document should contain the following sections.
1. Scope
Goals, major functions, system components2. Size and effort estimates
Historical sources
Size estimation - LOC
Effort estimation - man/months3. Risk management
Project risks
Risk Table and RMMM plan for each risk
4. Schedule
Task breakdown
Task network
Gannt chart5. Organization
Team shtructure
Team member responsibilities6. Tracking and control
Methods to be used - e.g. tracking table
QA methods to be used (leave this blank for now since