(Due date: Due the short time frame forthe project, this deliverable will be due the third class meeting, Thursday, 10/7/99 Planning and Scheduling
Note new deadline: 10/12/99, Tuesday, in class)The planning document should contain the following sections.
1. Scope
Goals, major functions, system components2. Size and effort estimates
Historical sources
Size estimation - LOC
Effort estimation - man/months3. Risk management
Project risks
Risk Table and RMMM plan for each risk
4. Schedule
Task breakdown
Task network
Gannt chart5. Organization
Team shtructure
Team member responsibilities6. Tracking and control
Methods to be used - e.g. tracking table
QA methods to be used (leave this blank for now since
we have not yet covered them in class)