include 'header.php' ?> Additional problem for homework Set 2
Critical Path Analysis
Find the critical path through the sets of gates. You should draw the gate layout as a part of your answer. Use the following delays:
Your answer should be of the form:
Critical Path = a-> h-> t-> .... etc
Total delay = 2 + 2 + 2 + ... etc
B) Inputs are a, b, c, d, e, f, g, h, i and the final outputs are t and p.